SETTLERS & ST ALBANS ROADS

August 2025 to Current - Hawkesbury City Council

 

Description:

Embankment Stabilisation Works: Embankment slip reinstatement including construction of sandstone retaining wall, supply and installation of rock revetments alongside the Hawkesbury River, Installation of sandstone boulders, soil nails and G65/3 mesh, Guardrail installation with the leading and trailing terminals, pavement reconstruction and all other associated works.

 

Road Rehabilitation Works: Flood Recovery Road Package including the reinstatement of approx. 14,000 sqm of the damaged road pavement, Borehole investigation of existing pavements, clearing and grubbing along the shoulder and table drains, In-situ stabilisation of base material, two coat sealing works, Clearing of existing pits and pipe culverts and all other associated works.

© 2023 by Jay & Lel Civil Contractors Pty Ltd